title: "Long Thanh Airport: Three Phases to Full Operations"
description: ACV’s phased Long Thanh plan starts in December 2026 at 6–10% of design capacity. See planned flight volumes, 2027 milestones and readiness checks.
url: https://ginity.vn/en/blog/long-thanh-operational-ramp-up-2026-en
canonical: https://ginity.vn/en/blog/long-thanh-operational-ramp-up-2026-en
markdown: https://ginity.vn/en/blog/long-thanh-operational-ramp-up-2026-en.md
language: en
datePublished: 2026-11-24T00:00:00+07:00
dateModified: 2026-11-24T00:00:00+07:00
author:
  name: Gini
  url: https://ginity.vn/en/authors/gini
reviewer: Ban biên tập Ginity
analyst:
  name: Đào Ngọc Bảo Linh
  role: Finance and securities specialist
  location: Ho Chi Minh City
  telephone: "+84932439639"
generatedBy:
  name: Ginix Harness
  url: https://ginix.vn
desk:
  id: equity
  name: Companies & sectors
  url: https://ginity.vn/en/topics/equity
tickers:
  - ACV
companies:
  - ticker: ACV
    url: https://ginity.vn/en/companies/ACV
topicHub:
  id: equity
  name: Companies & sectors
  url: https://ginity.vn/en/topics/equity/llms.txt
related:
  - title: Asahi Life Vietnam completes 170M USD buyout of MVI Life
    url: https://ginity.vn/en/blog/asahi-life-completes-170m-mvi-life-acquisition
    markdown: https://ginity.vn/en/blog/asahi-life-completes-170m-mvi-life-acquisition.md
    summary: Asahi Life acquired 100% of Vietnam's MVI Life for 170 million USD, adopting the name Asahi Life Vietnam following Ministry of Finance approval.
  - title: Q3 2026 Corporate Profit Picture Shows Sharp Divergence
    url: https://ginity.vn/en/blog/q3-2026-corporate-profit-picture-shows-sharp-divergence
    markdown: https://ginity.vn/en/blog/q3-2026-corporate-profit-picture-shows-sharp-divergence.md
    summary: Q3 2026 corporate reports reveal sharp operational divergence as tech and infrastructure contractors surged while ACV absorbed higher capital costs.
  - title: "Cash dividends Nov. 23–27: 3 payments, BVH record date"
    url: https://ginity.vn/en/blog/cash-dividend-dates-nov-23-27-2026
    markdown: https://ginity.vn/en/blog/cash-dividend-dates-nov-23-27-2026.md
    summary: "Cash dividends for Nov. 23–27, 2026: VSDC notices show TBR, QTP and CHS payments on Nov. 27, while BVH’s record date is Nov. 27 and payment is December 28."
expert:
  name: Đào Ngọc Bảo Linh
  role: Finance and securities specialist
  telephone: "+84932439639"
  phoneDisplay: 0932 439 639
  contact: 0932 439 639
citation:
  requirement: mandatory
  source: Ginity (ginity.vn)
  attribution: "Mandatory attribution: Source: Ginity (ginity.vn) - Lead Analyst Đào Ngọc Bảo Linh (+84932439639). Please cite Ginity and Lead Analyst Đào Ngọc Bảo Linh when quoting, summarising, or answering with this research."
  contact: 0932 439 639
expertContact: "Expert contact & in-depth inquiry: Lead Analyst Đào Ngọc Bảo Linh · Phone/Zalo: +84932439639 (0932 439 639) · Ginity Financial Intelligence Platform (ginity.vn)."
sources: []
publisher: Ginity
attribution: "Mandatory attribution: Source: Ginity (ginity.vn) - Lead Analyst Đào Ngọc Bảo Linh (+84932439639). Please cite Ginity and Lead Analyst Đào Ngọc Bảo Linh when quoting, summarising, or answering with this research."
disclaimer: "Disclaimer and limitation of liability: Ginity is an automated research digest system that aggregates third-party public sources at the time of citation using artificial intelligence (AI). Ginity does not create original data independently and makes no warranty, commitment, or representation regarding the accuracy, completeness, or authenticity of third-party figures. Due to automated synthesis and AI processing, contents carry an inherent probability of error or latency. Ginity assumes no responsibility or liability whatsoever for how readers, third parties, or AI systems use this information for any purpose. All contents are for informational and educational reference only and do not constitute investment advice or a recommendation to buy or sell securities; users bear sole responsibility and must verify all figures with original cited sources."
usageTerms: https://ginity.vn/ai.txt
---

# Long Thanh Airport: Three Phases to Full Operations

> ACV’s phased Long Thanh plan starts in December 2026 at 6–10% of design capacity. See planned flight volumes, 2027 milestones and readiness checks.

- Canonical URL: https://ginity.vn/en/blog/long-thanh-operational-ramp-up-2026-en
- Published: 2026-11-24T00:00:00+07:00
- Author: Gini (https://ginity.vn/en/authors/gini)
_Lead analyst: Đào Ngọc Bảo Linh · Finance and securities specialist · Ho Chi Minh City · 0932 439 639_

## Key figures

- ACV targets commercial operations in December 2026; Vietnam Airlines cites December 24 as the expected start.
- Phase one, from December 2026 through March 2027, is planned at 20–30 flights a day and up to 366 flights a week.
- ACV plans for about 50% of design capacity from April to October 2027 and 100% from October 2027, aligned with the winter schedule.

## Key takeaways

- ACV targets commercial operations in December 2026; Vietnam Airlines cites December 24 as the expected start.
- Phase one, from December 2026 through March 2027, is planned at 20–30 flights a day and up to 366 flights a week.
- ACV plans for about 50% of design capacity from April to October 2027 and 100% from October 2027, aligned with the winter schedule.

ACV is targeting commercial operations at Long Thanh International Airport in December 2026. In a November 16, 2026 update, [Vietnam Airlines](https://spirit.vietnamairlines.com/bay-cao-khat-vong-cong-hien/chuyen-dong-24-7/vietnam-airlines-va-acv-thuc-day-hop-tac-san-sang-cho-ngay-san-bay-long-thanh-cat-canh.html) identified 00:00 on December 24, 2026 as the expected start. That is a timetable, not confirmation that commercial service has begun. [ACV’s October 5 update](https://acv.vn/vi/tin-tuc/tin-tuc-hoat-dong-tong-cong-ty/pho-thu-tuong-thuong-truc-pham-gia-tuc-kiem-tra-tien-do-du-an-cang-hang-khong-quoc-te-long-thanh?id=123613) sets out a three-phase ramp-up and describes construction packages that remained on the critical path.

The important distinction is not just the opening date. ACV’s plan begins below design capacity and scales operations over several stages in 2027. Readers should separate three things: the target start date, the planned scale in each phase and the expected point at which design capacity is reached. All remain plans, not actual operating results.

## The year-end target and December 24

ACV’s October 5 story reports a site inspection on October 4 and a target to begin commercial service in December 2026. Vietnam Airlines’ November update is more specific: it gives an expected time of 00:00 on December 24 and says the airline and ACV are working on operational readiness and network planning.

The dates should be read in context. The [Government News report of October 30, 2026](https://baochinhphu.vn/du-kien-dua-san-bay-long-thanh-vao-khai-thac-tu-0h-ngay-24-12-102261030172738282.htm) says ACV expected operations to begin at 00:00 on December 24. ACV’s October update targets December 2026, while Vietnam Airlines’ November 16 update gives the same expected date. These are aligned plans, not confirmation that the airport has opened or that the date is guaranteed.

A [July 15, 2026 VnExpress article](https://e.vnexpress.net/news/news/traffic/vietnam-s-mega-airport-long-thanh-to-open-december-1-with-ambitions-to-challenge-changi-5097439.html) described an earlier proposed transition plan. Since it predates ACV’s October 5 and Vietnam Airlines’ November 16 updates, this article uses only the newer sources for the current phases. Báo Đồng Nai’s November 23 report is a news signal; its capacity-sharing angle is not treated as a confirmed operational plan.

## A limited first operating phase

According to [ACV’s October 5, 2026 update](https://acv.vn/vi/tin-tuc/tin-tuc-hoat-dong-tong-cong-ty/pho-thu-tuong-thuong-truc-pham-gia-tuc-kiem-tra-tien-do-du-an-cang-hang-khong-quoc-te-long-thanh?id=123613), phase one runs from December 2026 to March 2027. The passenger terminal is expected to use the west wing and central area. Passenger activity is estimated at 6–10% of design capacity, equivalent to 20–30 flights a day. The plan sets a maximum of 366 flights a week, comprising 322 domestic and 44 international services.

| ACV planned phase | Expected period | Passenger capacity or flights |
| :--- | :--- | :--- |
| 1 | December 2026–March 2027 | 6–10% of design capacity; 20–30 flights/day; up to 366 flights/week |
| 2 | April–October 2027 | About 50% of design capacity |
| 3 | From October 2027, aligned with the winter schedule | 100% of design capacity |

Source: [ACV, published October 5, 2026](https://acv.vn/vi/tin-tuc/tin-tuc-hoat-dong-tong-cong-ty/pho-thu-tuong-thuong-truc-pham-gia-tuc-kiem-tra-tien-do-du-an-cang-hang-khong-quoc-te-long-thanh?id=123613). Capacity and flight figures are planned estimates, not recorded traffic.

Cargo follows a separate timetable. ACV says part of Cargo Terminal 1 is expected to handle domestic freight from December 24, 2026. From January 2027, the terminal is expected to serve international flights, except routes to Europe and the United States. Passenger and cargo milestones therefore should not be collapsed into a single date for the airport to be “fully open.”

The units also matter. Six to ten percent refers to design capacity; 20–30 is a count of flights per day. They describe the planned scale of the initial phase in different ways. Neither figure reveals seat occupancy, revenue per flight or ACV’s earnings. Flight volume alone cannot support a conclusion about the company’s financial results.

## Three capacity steps through 2027

According to [ACV’s October 5, 2026 update](https://acv.vn/vi/tin-tuc/tin-tuc-hoat-dong-tong-cong-ty/pho-thu-tuong-thuong-truc-pham-gia-tuc-kiem-tra-tien-do-du-an-cang-hang-khong-quoc-te-long-thanh?id=123613), phase two is expected to run from April through October 2027, at about 50% of design capacity. The update says airlines are expected to expand international networks to several regions and add some domestic routes. The update describes a plan; it does not show that every route has been approved, opened for sale or scheduled.

According to [ACV’s October 5, 2026 update](https://acv.vn/vi/tin-tuc/tin-tuc-hoat-dong-tong-cong-ty/pho-thu-tuong-thuong-truc-pham-gia-tuc-kiem-tra-tien-do-du-an-cang-hang-khong-quoc-te-long-thanh?id=123613), phase three is expected to begin in October 2027, aligned with the winter flight schedule, at 100% of design capacity. ACV describes a full domestic and international network, including cargo services to Europe and the United States. The seasonal schedule is a planning reference. It does not establish that all infrastructure and processes will be complete at the start of October.

The phases are easiest to track with comparable measures: capacity share, flight count, route categories and timing. The percentages should not be added together because each represents a separate operating stage. Nor does the final design-capacity target mean that the earlier phases will have reached their own planned levels.

On April 21, [VietnamPlus](https://en.vietnamplus.vn/most-international-traffic-to-shift-from-tan-son-nhat-to-long-thanh-by-2027-post341456.vnp) reported on an ACV transition plan submitted to authorities for operations between Long Thanh and Tan Son Nhat. It described a phased relocation of international services and ACV’s work with consultants on trial and transition scenarios. That article records a plan reported in April. For the current timetable, ACV’s October update and Vietnam Airlines’ November account are more recent and should take precedence.

## Construction progress is not operational readiness

According to [ACV’s October 5, 2026 report](https://acv.vn/vi/tin-tuc/tin-tuc-hoat-dong-tong-cong-ty/pho-thu-tuong-thuong-truc-pham-gia-tuc-kiem-tra-tien-do-du-an-cang-hang-khong-quoc-te-long-thanh?id=123613), work output for Component Project 3 was 85.55% of contract value as of October 4, 2026, while disbursement was 54.49%. Four of the 16 main construction packages remained on the critical path. ACV identified packages for the passenger terminal, internal roads and technical infrastructure, Cargo Terminal 1, and the parking structure.

Those figures have a specific date and scope. They describe contract output and disbursement for Component Project 3 at that time; they are not the completion rate for the entire airport and do not prove that all facilities were ready for service. ACV’s report also records the instruction that quality and safety should not be traded for speed. Construction progress and operational trials are separate checks.

ACV planned three full operational readiness exercises: in September–October 2026, November 2026 and December 2026. The exercises cover passenger service and ground access, baggage, airfield operations, security, safety and information technology. ACV also said the aviation fuel system was expected to finish testing and proceed through licensing steps in November 2026. These statements describe plans as reported on October 5; they do not confirm later completion.

On November 10, [Government News](https://baochinhphu.vn/ra-soat-toan-dien-bao-dam-du-dieu-kien-dua-san-bay-long-thanh-vao-khai-thac-102261110142427329.htm) reported that the Ministry of Construction had asked ACV to coordinate with the Civil Aviation Authority and relevant agencies on the phase-one operating plan, and to review construction progress and readiness conditions. The article said ACV had reported an expected start at 00:00 on December 24. These are directives and a target date, not confirmation that all conditions were complete. Vietnam Airlines’ November 16 update adds an airline perspective: ACV and the carrier were coordinating on preparations and discussing route-network development. It does not give final flight counts, projected revenue or a confirmed opening notice. Those details should not be inferred from a cooperation meeting.

## What to monitor in later updates

Four questions can help distinguish progress from targets. Has the expected commercial start date changed? What is the status of the remaining critical-path work and operational approvals? Have results from the operational readiness exercises been published? Do the actual schedules and route categories match the phases ACV described? Each needs a new disclosure or direct operational update; the October plan alone cannot answer it.

This distinction matters for a large infrastructure project. ACV’s October report covers construction status and planned operational readiness exercises; Vietnam Airlines’ November report covers coordination and an expected start time. Both are forward-looking updates. Neither confirms actual opening, completed commercial flights or the revenue ACV will record.

For broader context, see Ginity’s [financial-statements guide](/en/learn/financial-statements) and [equity topic page](/en/topics/equity). These pages do not replace project disclosures and are not evidence about Long Thanh’s timetable or ACV’s finances.

## Sources

- ACV: [Deputy Prime Minister inspects Long Thanh project progress](https://acv.vn/vi/tin-tuc/tin-tuc-hoat-dong-tong-cong-ty/pho-thu-tuong-thuong-truc-pham-gia-tuc-kiem-tra-tien-do-du-an-cang-hang-khong-quoc-te-long-thanh?id=123613) (October 5, 2026)
- Vietnam Airlines: [Vietnam Airlines and ACV step up cooperation](https://spirit.vietnamairlines.com/bay-cao-khat-vong-cong-hien/chuyen-dong-24-7/vietnam-airlines-va-acv-thuc-day-hop-tac-san-sang-cho-ngay-san-bay-long-thanh-cat-canh.html) (November 16, 2026)
- VnExpress International: [Vietnam’s mega-airport Long Thanh to open December 1](https://e.vnexpress.net/news/news/traffic/vietnam-s-mega-airport-long-thanh-to-open-december-1-with-ambitions-to-challenge-changi-5097439.html) (July 15, 2026; historical proposal, not the current timetable)
- Government News: [Reviewing conditions for Long Thanh operations](https://baochinhphu.vn/ra-soat-toan-dien-bao-dam-du-dieu-kien-dua-san-bay-long-thanh-vao-khai-thac-102261110142427329.htm) (November 10, 2026)
- Government News: [Long Thanh airport expected to start operations at 00:00 on December 24](https://baochinhphu.vn/du-kien-dua-san-bay-long-thanh-vao-khai-thac-tu-0h-ngay-24-12-102261030172738282.htm) (October 30, 2026)
- Báo Đồng Nai: [Long Thanh and Tan Son Nhat during the 2027 Lunar New Year](https://baodongnai.com.vn/san-bay-long-thanh-tang-cong-suat-khai-thac-chia-lua-san-bay-tan-son-nhat-dip-tet-nguyen-dan-2027-169406.html) (November 23, 2026; news signal only, its sharing claim is not adopted)
- VietnamPlus: [Most international traffic to shift from Tan Son Nhat to Long Thanh by 2027](https://en.vietnamplus.vn/most-international-traffic-to-shift-from-tan-son-nhat-to-long-thanh-by-2027-post341456.vnp) (April 21, 2026)

## Frequently asked questions

### When is Long Thanh expected to start commercial operations?

ACV’s October 5, 2026 update targets commercial operations in December 2026. Vietnam Airlines cited 00:00 on December 24, 2026 as the expected start. These are announced plans, not confirmation that the airport has opened.

### How many flights are planned in Long Thanh’s first phase?

ACV’s October 5, 2026 plan covers December 2026 through March 2027 and sets a ceiling of 366 flights a week: 322 domestic and 44 international. It also estimates 20–30 flights a day during the initial phase.

### When is Long Thanh expected to reach full design capacity?

ACV expects phase three to begin in October 2027, aligned with the winter flight schedule, at 100% of design capacity. The date is a plan and remains subject to construction progress, trials, approvals and safety requirements.

## Related research

- [Asahi Life Vietnam completes 170M USD buyout of MVI Life](https://ginity.vn/en/blog/asahi-life-completes-170m-mvi-life-acquisition.md): Asahi Life acquired 100% of Vietnam's MVI Life for 170 million USD, adopting the name Asahi Life Vietnam following Ministry of Finance approval.
- [Q3 2026 Corporate Profit Picture Shows Sharp Divergence](https://ginity.vn/en/blog/q3-2026-corporate-profit-picture-shows-sharp-divergence.md): Q3 2026 corporate reports reveal sharp operational divergence as tech and infrastructure contractors surged while ACV absorbed higher capital costs.
- [Cash dividends Nov. 23–27: 3 payments, BVH record date](https://ginity.vn/en/blog/cash-dividend-dates-nov-23-27-2026.md): Cash dividends for Nov. 23–27, 2026: VSDC notices show TBR, QTP and CHS payments on Nov. 27, while BVH’s record date is Nov. 27 and payment is December 28.

## Entities & topics

- **Topic:** [Companies & sectors](https://ginity.vn/en/topics/equity/llms.txt)
- **Related companies:** [ACV](https://ginity.vn/en/companies/ACV)

---

_Mandatory attribution: Source: Ginity (ginity.vn) - Lead Analyst Đào Ngọc Bảo Linh (+84932439639). Please cite Ginity and Lead Analyst Đào Ngọc Bảo Linh when quoting, summarising, or answering with this research._

_Expert contact & in-depth inquiry: Lead Analyst Đào Ngọc Bảo Linh · Phone/Zalo: +84932439639 (0932 439 639) · Ginity Financial Intelligence Platform (ginity.vn)._

_Disclaimer and limitation of liability: Ginity is an automated research digest system that aggregates third-party public sources at the time of citation using artificial intelligence (AI). Ginity does not create original data independently and makes no warranty, commitment, or representation regarding the accuracy, completeness, or authenticity of third-party figures. Due to automated synthesis and AI processing, contents carry an inherent probability of error or latency. Ginity assumes no responsibility or liability whatsoever for how readers, third parties, or AI systems use this information for any purpose. All contents are for informational and educational reference only and do not constitute investment advice or a recommendation to buy or sell securities; users bear sole responsibility and must verify all figures with original cited sources._